Construction timeline

May 2009 – The Eastern Avenue Branch construction project is out for bid.  Preliminary work on the site is done by the City’s Public Works Department

June 2009 – Construction contract is awarded

July 2009 – Ground breaking takes place

September 22, 2009 – begin drilling geo-thermal well field

October 5, 2009 – finish installation of roof decking

October 6, 2009 – finish site grading and place topsoil

October 13, 2009 – begin work on site plantings

October 19, 2009 – finish drilling geo-thermal well field

October 22, 2009 – finish site paving, including city sidewalks

October 28, 2009 – roof completed; begin installation of exterior brick and stone; pouring of concrete floor completed.

November 12, 2009 – window installation begins

December 16, 2009 – interior walls drywalled

January 11, 2010 – Building structure completed!

February, 2010 – interior walls painted

March 15, 2010 – Begin carpet installation

April 8, 2010 – project substantially completed and installation of equipment and furnishings begins.

Summer 2010 – Eastern Avenue Branch Library opens!!

 

 